Tlou Energy Successfully Completes Top-Hole Drilling in CBM Project
Anita Riotta
Company News- 2 min read
10:54, 4th December 2018

Tlou Energy FOLLOW, the gas-to-power project development company focused on coal bed methane (CBM) natural gas in Botswana, has successfully completed top-hole drilling at its Lesedi CBM Project.

The top-hole sections were drilled for both the vertical and lateral wells at Lesedi, each being finished on time and on budget. Now, the company is focused on preparations for drilling lateral wells for their production pods, Lesedi 3 and Lesedi 4.

The program is set to continue into early 2019.

The aim here is to confirm the gas flow rate in this area before beginning any development operations. As such, the wells are being drilled in the area proposed for initial project development.

The Lesedi CBM Project, if successful, will constitute the company’s first gas-to-power project.